Construction Update

Cascade Medical Center’s Addition and Modernization

Project Update, March 3, 2010

The Cascade Medical Center’s new Project consists of an addition to and modernization of the existing facility, located at 817 Commercial Street, Leavenworth, Washington.  The purpose is to provide an updated patient care facility that will provide expanded services that are in line with latest practices and codes which is not possible in the confined space of the existing facility.  The total Project Cost of the new facility including all systems, furnishings, equipments, fees, permits and sales tax is $14.4 million and is funded in part by community approved general obligation bonds.

The addition will include a partial daylight lower level of approximately 5,530 sf, a main level of approximately 8,263 sf and an upper level of approximately 6,650 sf with an additional roughed-in area of 1,613 sf for clinic expansion in the future.  The lower level will include a new covered ambulance parking area, mechanical and electrical rooms and storage for the hospital’s maintenance equipment.  The main level addition will house the relocated Acute Care patient rooms and their support spaces and part of the relocated and expanded Emergency Department.  The upper floor of the addition will house the relocated and expanded provider’s clinic with elevator access.

The lower level of the existing hospital will receive minor remodeling and upgraded finishes and will house the hospital support spaces such as kitchen, staff dining, staff lockers and showers, Central Supply, Medical Records, a classroom and storage areas.

The main level of the existing hospital building will be almost completely remodeled.  The structure will be upgraded to comply with current snow loads, and fireproofed to comply with current Life Safety codes.  The existing facility’s mechanical and electrical will be completely upgraded to comply with current codes.  The waiting area, Radiology, Lab, Physical Therapy, portions of Emergency and Acute Care will be relocated and upgraded to provide better service and easier access for patients and better work flow for staff.

The entire hospital facility and the new clinic will be fire sprinkled to comply with current Life Safety codes.

The existing clinic at the east end of the site will have finishes upgraded and some very minor remodeling as it is converted to office space for hospital administration.  The exterior will be upgraded to comply with the City’s Bavarian design standards.

Sitework will include adding a new patient drop-off at the north end of the building off Commercial Street, relocated Emergency Department ambulance and patient entries at the west side of the site of 8th Street including parking at the northwest corner of the site and upgrading the parking at the south side of the site.  Sitework will also include new landscaping.

Cascade Medical Center awarded their Addition and Modernization project to Levernier Construction of Spokane, Washington on August 11, 2009 and work was commenced shortly thereafter.

Levernier has focused on the Phase 1, construction of the new addition, which will house the new upper level clinic, new main level acute facility, and lower level Ambulance and mechanical and electrical areas with anticipated completion scheduled for late August this year.

Mild Weather has allowed construction of the Cascade Medical Center’s new facility to continue unhampered as Levernier Construction moves forward toward completion of the Phase 1 addition.

To date, the addition’s structural work has been completed including all floors, roof deck and structural glu-laminated beams. Fire proofing of the structural elements is anticipated to be completed this week.  All floors have been poured; all mechanical air handling units have been set and the mechanical subcontractor is in the process of running HVAC ductwork.  The elevator tower has been installed as well as stairs at both ends of the addition are complete.  The electrical subcontractor is currently in the process installing electrical branch conduits as the interior walls are being constructed, and plumbing is currently being installed.

Throughout the Spring, the Community will be able to see the installation of exterior wall framing and sheathing as well as installation of the roof system.

The District anticipates installation of various hospital related systems commencing mid-July of this year with installation of furnishings and equipment scheduled for the latter part of August for an anticipated occupancy of the new clinic and acute area by early September.

Following completion of Phase 1 and the District’s move-in, Levernier Construction will commence Phase 2 which involves renovations and modernization to the lower and main levels of the existing hospital facility, addition of the main entry/lobby, and Bavarian upgrades along Commercial Street.  Phase 3 will follow shortly thereafter and include renovations of the front of the existing hospital to house the new Physical Therapy Department and Therapy Pool and construction of the Laboratory facilities.