Cascade Medical Center awarded their Addition and
Modernization project to Levernier Construction of Spokane, Washington
on August 11, 2009 and work commenced shortly thereafter.
Levernier has focused on the Phase 1, construction of the
new addition, which will house the new upper level clinic, new main
level acute facility, and lower level ambulance and mechanical and
electrical areas with anticipated completion scheduled for late August
this year.
To date, the Addition footings and foundations are
complete, as well as the North elevator structure. Eighty percent of
structural steel and floor decking is complete, the lower level main
HVAC units have been set, and electrical service rough-in is complete.
Levernier is currently completing the South stairway casing and when
complete, they will finish erection of structural steel. Mechanical and
electrical installations continue.
Following completion of Phase 1 and the District’s
move-in, Levernier will commence Phase 2, which involves renovations and
modernization to the lower and main levels of the existing hospital
facility and the addition of the main entry, and lobby along Commercial
Street.
Phase 3 will follow shortly thereafter and will include
renovations of the existing hospital adjacent to Commercial Street and
house the new Physical Therapy department, which will include the
therapy pool as well as upgrading the exterior facades to comply with
Leavenworth’s Bavarian Theme.
|